The market redevelopment consists of construction of a new F&V market whilst the existing is gradually migrated into the new with demolition taking place in phases. Whilst the new market is constructed, the traders will continue to trade from their existing units.
The scope of the Works is the design, construction, completion, testing and commissioning of the Works, comprising:
Demolition of Existing Market Buildings & Infrastructure
Construction of new Buildings for the Fruit & Vegetable Market
Construction of new Flower Market/ Food Exchange Building – Food Exchange completed
Refurbishment of existing Multi-Storey Car Park – Completed· Construction of new Waste Compound,
Sports Pitches above and Adjacent Welfare & Plant Areas – Completed
Construction of new Interim Flower Market & Single Deck Car Park – Completed
Construction of new Infrastructure & Services, Roads and Hardstandings, Toll Plazas, etc.
Construction of a new security lodge – Completed
Phased construction of the new trader blocks. Block A & B1 are complete, the current phase is B2
Interim Construction of the Permanent Flower Market to take the form of Interim Distribution Units – Completed
All works are to be undertaken in a phased sequence.
Due to the phased execution of the works the duration of the scheme is expected to be 10 years, 6 months.
Fruit & Vegetable Market -The new Fruit & Vegetable Market blocks, approximately 50,000m2 in area, will be located to the west of the main Market Site; the buildings being single storey, steel framed clad with profile sheeting, floors are resin coated concrete and the units are sub-divided with composite panels.
The tenant units are formed as a shell with independent services.
Activity
Groundworks including foundations and drainage.
Steelwork – Frame erection.