2 Form Primary School with places for 462 pupil and 12 SEN places. Project value to Kier £16m. We are currently in week 26 of 65 weeks. The building is of piled foundation, ground beams and pile caps with insitu concrete ground floor slab. Steel frame and precast planks with structural concrete topping. Hot melt roof membrane, with some plants and PV panels on the roof. External walling of SFS with brick cladding and punch windows. Full M&E and FF&E fit out.
Short presentation about the project and team, followed by site walk about. Visitors PPE is available and will need to be worn including hard hat, safety boots, glasses, gloves and hi viz vest.